Located in Framingham MA, Fuller Middle School recently constructed a new three-story building. This project provided students and faculty with new classrooms as well as a new learning commons, cafeteria, gym, auditorium and STEM instructional areas.
MMS was asked to provide a chilled water pump house for an air-cooled chiller package.
- Penthouse included: (2) pumps and accessories, VFD’s, an expansion tank, an air separator, a buffer tank, a glycol feeder, a unit heater, dampers and fans as well as associated electrical and controls scope.
- This client had limited mechanical space within the building and decided to utilize roof real estate for their chilled water plant and pump house.
- These units were installed in June 2021 with full occupancy of the building in August 2021.
- Vertical: K-12